Sorry to ask this again, but what are the ideal rock sizes for base and top layers for gravel tees? I seem to remember something along the lines of #57 for the sub layer and #21a crusher run for the top. We are installing some new gravel tees (framed and tamped) and I want to make sure it's right.
Recommended depth of the layers?
Also, is there any benefit to lightly watering the top layer between tampings or afterwards to hasten the compacting process?
If someone could give me the dummies version of the process that would be awesome :thmbup:
As an aside, the park doesn't let us put in concrete so that isn't an option, and the areas we are doing this are uneven/very muddy so the natural tees are a nightmare.
Any info would be greatly appreciated.
Recommended depth of the layers?
Also, is there any benefit to lightly watering the top layer between tampings or afterwards to hasten the compacting process?
If someone could give me the dummies version of the process that would be awesome :thmbup:
As an aside, the park doesn't let us put in concrete so that isn't an option, and the areas we are doing this are uneven/very muddy so the natural tees are a nightmare.
Any info would be greatly appreciated.